ADU Site Prep & Utilities in McKinney: What’s Actually Involved
ADU Site Prep & Utilities in McKinney runs $45,000 – $130,000 for the site work side of a detached or attached unit, and most projects land in the 6-to-14-week range from first excavation to final utility inspection. That covers grading, the pad or pier foundation, water and sewer runs, the electrical service and meter, and gas if you’re running it. It does not cover the structure itself. Call (888) 343-9048 and we’ll walk your lot line with you before anyone quotes a number.
How We Run the Job, Stage by Stage

Most contractors quote site prep as a lump number and then disappear for two weeks. Here’s the actual sequence so you know what day one looks like and when you need to make a decision.
Stage 1: Lot Survey and Utility Locate (Days 1 – 3)
We start by pulling the plat and confirming setbacks, easements, and where the existing water, sewer, and electric actually enter the main house. Texas811 marks the buried lines, and we hand-dig to confirm depth on anything the marks don’t cover. You’ll need to confirm your target ADU footprint at this point, because moving it ten feet later costs real money. Grading follows within a day or two once the footprint is locked.
Stage 2: Excavation and Grading (Days 4 – 8)
Cut and fill to bring the pad to finished grade, with drainage sloped away from both the ADU and your main house. On McKinney’s blackland clay we over-excavate and re-compact in lifts, because the native soil swells and shrinks with the seasons and a pad built on undisturbed clay will move. This is also when we trench for water, sewer, and conduit. You’ll decide the pad elevation here, and that decision drives how much dirt leaves the site.
Stage 3: Foundation and Utility Rough-In (Weeks 2 – 4)
Slab on grade, pier and beam, or a post-tension slab depending on the soil report and the unit’s footprint. While the concrete cures, we run the water line, sewer lateral, and electrical conduit to the tie-in points. This is where most of the surprises live – an old clay sewer line that won’t handle the added load, or a panel with no spare capacity. You’ll choose the foundation type and confirm the tie-in points with a licensed plumber and electrician.
Stage 4: Inspections (Weeks 4 – 5)
The city inspects the underground plumbing, then the electrical rough-in, then the foundation. Each inspection is a separate scheduled visit and a failed one can push the timeline a week. We build schedule float around the inspection window and don’t pour or backfill until each one passes.
Stage 5: Utility Bring-Up and Final Grade (Weeks 5 – 7)
The meter set, the final tie-in to the house service, and the finish grading, including any French drain or swale the lot needs. You’ll pick fixtures at this stage – a Sterling or Grohe rough-in valve set now so the finish trim goes in without a second visit later. Sod and landscaping go last, once the trenching is closed and settled.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Actually Choose Between
None of these are cosmetic. Each one changes the number and the long-term maintenance load on a McKinney lot.
- Slab on grade vs. pier and beam. A slab is faster and cheaper up front. Pier and beam gives you a service cavity for plumbing and easier repair on expansive clay, but costs more and needs skirting and ventilation detail. On heavily treed or grade-variable lots, pier and beam usually wins.
- Utility trench depth and conduit. Running direct-burial cable is cheaper; running conduit lets you pull wire later without digging. On a long drive to the back of the lot, conduit pays for itself the first time something fails.
- Electrical service size. A 60-amp subpanel suits a basic one-bedroom unit; a full electric range, heat pump, and EV charger will need 100 amps or more. Ask your electrician to run the load calculation before you commit.
- Sewer tie-in vs. grinder pump. Gravity is best. If the ADU sits below the main house’s sewer invert, a grinder pump is the fallback and adds ongoing maintenance and noise.
- Grading and drainage detail. Basic slope is standard; a French drain or swale along the low side of the lot costs more but prevents water pooling against the new foundation.
What ADU Site Prep & Utilities Costs in McKinney, TX

Plan on $45,000 – $130,000 for the site and utility scope, with the structure billed separately. The low end is a flat, straightforward lot on a short run from the house. The high end is a back-lot build with long trench runs, a grinder pump, and heavy grading.
What moves the number:
- Utility run distance. Moving water, sewer, and power from the far side of the house to the back of the lot can double the trenching and material.
- Foundation type and soil. Pier and beam on expansive clay runs higher than a plain slab.
- Sewer conditions. A gravity tie-in is the baseline; a grinder pump and lift station adds cost and maintenance.
- Grading volume. Sloped lots mean more cut, fill, and haul-off.
- Permit scope. More inspections and separate trade permits add fees and schedule time.
A written estimate should list every line – excavation, foundation, plumbing rough, electrical rough, gas, permits, and final grade – with a fixed number and no change orders for the scope shown. What it typically excludes is the ADU structure itself, finish landscaping, and any unexpected repair like a collapsed sewer line found during trenching.
See the difference
Before
After
Before
After
Before
AfterWhat McKinney Homes Specifically Do to This Job
McKinney sits on blackland prairie clay, and that fact drives the entire foundation decision. The soil swells in spring and shrinks in the July heat, so we design pads and pier depths around seasonal movement rather than assuming the ground is stable. On the older 75069 lots near the historic downtown square, the existing water, sewer, and electric are often undersized for an added unit, and the home’s era means the utility tie-in needs a careful look before we commit. In the 75070 and 75071 corridors – Stonebridge Ranch, Adriatica, and the newer subdivisions – the lots are typically tract-built on a standard grid, but HOA rules on accessory structures and fencing can add a review step before permitting. Homeowners often pair this with Concrete Driveways & Concrete Work in McKinney so the new unit has a proper access apron, and some go with Paver Driveways in McKinney if the HOA prefers pavers on the visible frontage.
Our Approach on a McKinney Lot
We do the site work and utilities as one coordinated job, so the trench, the pad, and the trades are scheduled together rather than strung out across three separate contractors. Our technicians have up to 12 years of experience on this kind of ground-up utility and foundation work, and every one is background-checked and arrives in uniform. The whole scope sits under our 730-Day Done Right Promise and comes with upfront pricing – the number on the quote is the number you pay, with 0% financing for 18 months and $1,000 off projects over $10,000 available. When the wider project is on the table, this fits into a full Home Additions & ADU in McKinney build, and you can see that full Home Additions & ADU service on our main page. We cover McKinney and the surrounding area, including Melissa, Allen, Princeton, and Fairview.
Serving McKinney, TX – Our Local Coverage Area
We serve McKinney and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – ADU Site Prep & Utilities in McKinney
ADU Site Prep & Utilities typically runs 6 to 14 weeks, and the biggest swing factor is inspection scheduling with the city. Foundation and utility rough-in take the longest because each trade inspection has to pass before the next stage starts. Call (888) 343-9048 for a timeline built around your lot.
Yes. Grading, foundation, plumbing, and electrical all require separate permits and inspections in McKinney, and skipping them will stall the build and complicate resale. We pull the permits and schedule the inspections as part of the job. Call (888) 343-9048 to talk through the permit scope.
Sometimes, if the ADU sits close to the main house and the existing lines have capacity, but most detached units need new trenching and a new tie-in. We confirm that in the survey stage before you commit. Call (888) 343-9048 and we’ll assess your existing service.
The range is $45,000 – $130,000 for site and utilities, depending on run distance, foundation type, and grading. The structure is quoted separately. Call (888) 343-9048 for an exact quote – estimates are free.
Our 730-Day Done Right Promise covers the site and utility work for two years – if it’s not done right, we make it right. Calls are answered by a live person, 24/7. Call (888) 343-9048 to schedule your free estimate.
Get a Free On-Site Estimate

Bring us your lot and your ADU plan. We’ll walk the tie-in points, flag the grading and soil issues up front, and hand you a fixed, line-item estimate for the site prep and utilities in McKinney – no vague ranges, no change orders for the scope shown. Call (888) 343-9048, and a live person answers whenever you call.