Garage Conversion ADU in Melissa: What It Takes and What It Costs
A garage conversion ADU in Melissa usually runs $45,000 – $130,000 and takes about 4 to 7 months from first demo to final inspection. The lower end is a clean single-bay conversion with a bathroom and a kitchenette; the upper end is a full two-car buildout with a full kitchen, separate HVAC, upgraded finishes, and new utility tie-ins. Call (888) 343-9048 for a free on-site estimate before you commit to a budget.
How a Garage Conversion ADU Comes Together, Stage by Stage

Most contractors will tell you they “handle everything.” Here’s what that actually means, week by week, so you know what to expect and when your decisions are due.
Stage 1: Site review and design (weeks 1 – 3)
We walk the garage with you and measure what’s really there: slab condition, ceiling height, where the water heater and HVAC sit, whether the existing electrical panel can carry a second dwelling. You decide the footprint (keep the garage door opening or frame it in?) and the layout. That design goes to the city for permitting during this window, which is where timelines live or die in fast-growing Melissa.
Stage 2: Demo and rough-in (weeks 3 – 7)
The garage door comes off or gets framed behind, the slab gets inspected for cracks and moisture, and framing goes up for interior walls, the bathroom, and any new openings. Plumbing, electrical, and HVAC rough-ins happen here. This is the noisy, dusty phase, and it’s also where surprises surface: a slab that’s shifted on expansive clay, or a panel that needs upgrading to carry a kitchenette.
Stage 3: Rough inspections (week 7 – 9)
The city inspects framing, electrical, plumbing, and mechanical before anything gets closed up. We schedule these and meet the inspector on site. Nothing gets covered until it passes, which is why we pull permits rather than working around them.
Stage 4: Insulation, drywall, and finishes (weeks 9 – 18)
Insulation goes in with North Texas summers in mind, then drywall, texture, paint, flooring, cabinets, and fixtures. This is your longest decision window: countertop material, flooring, door style, lighting. We lock selections before this stage starts so nothing stalls the schedule.
Stage 5: Final inspection and punch list (weeks 18 – 24)
The final inspection clears the unit for occupancy, we walk the space with you, and we close out the punch list. Your 730-Day Done Right Promise starts here and covers workmanship for two full years, in writing.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape Your Garage Conversion ADU
Every conversion comes down to a handful of forks in the road. Here’s what you’ll actually pick between, and the honest trade-off on each.
- Slab-on-grade vs. raised floor: Keeping the existing slab saves $4,000 – $9,000 and skips a step, but it runs cooler in winter and needs a moisture barrier. A raised subfloor adds cost and ceiling-height loss but feels like a real room underfoot.
- Full kitchen vs. kitchenette: A kitchenette (sink, mini-fridge, microwave, no range) keeps the permit simpler. A full kitchen with a range hood and 240V circuit pushes you toward a panel upgrade and adds $8,000 – $18,000.
- Separate HVAC vs. mini-split vs. tie-in: A ductless mini-split is the most common choice for a single-room conversion and handles North Texas heat well. Tying into the house system is cheaper upfront but can starve the main house on a 105°F day.
- Garage door opening: Framing it in with siding and a window reads like a real addition. Keeping the door and building behind it is cheaper but looks like a converted garage from the street, and some HOAs won’t allow it.
- Exterior cladding: Matching the house matters here. Fiber cement or engineered siding in a custom profile blends better than standard lap siding, and paint-matched trim sells the illusion that the space was always there.
What a Garage Conversion ADU Costs in Melissa, TX

Plan on $45,000 – $130,000 for a garage conversion ADU in Melissa, with most single-bay jobs landing in the $55,000 – $80,000 range and two-car builds with full kitchens pushing past $100,000. Five variables decide where you land:
- Size and bay count: A single-bay conversion is roughly half the square footage of a two-car, and that gap drives framing, drywall, flooring, and finish costs proportionally.
- Plumbing distance: Bathrooms and kitchenettes need drain lines to the main sewer. The farther the run from the garage to the existing stack, the more slab gets cut, and that’s a $3,000 – $12,000 swing.
- Electrical capacity: If your panel has open breaker slots, you’re fine. If it needs an upgrade or a subpanel, budget $2,500 – $6,000.
- Finish level: Builder-grade finishes land near the low end. Quartz counters, custom cabinetry, and tile showers push toward the high end.
- Permit scope: A habitable-room conversion with a bathroom is a bigger permit package than a studio with no plumbing, and inspections reflect that.
A written estimate from us lists line items for demo, framing, rough-in trades, insulation, drywall, finishes, and permit fees, with the number you see being the number you pay. What it doesn’t cover: HOA application fees, any structural repair revealed after demo, and utility connection fees if the garage needs a new meter.
See the difference
Before
After
Before
After
Before
AfterWhat Melissa’s Housing Stock and Growth Mean for This Job
Most of the homes we convert garages in are less than 10 years old, in master-planned subdivisions off Highway 5 and around the Melissa Road corridor, which changes the work in a specific way: these garages were framed to hold cars, not people, and the slab was poured on expansive North Texas clay. We check for slab movement before we ever price a conversion, because a hairline crack that’s fine under a car becomes a finish problem under a bedroom floor. Melissa’s rapid growth also matters at the permit desk. The city is processing a wave of new construction permits, and phased utility installations mean we sometimes coordinate with more than one provider to confirm water and sewer tie-in capacity before the final inspection clears. That’s not a paperwork problem, it’s a scheduling one, and we build it into the timeline from day one. This work sits inside a bigger scope if you’re also adding on elsewhere, and it’s part of a full Home Additions & ADU in Melissa plan for a lot of our customers.
Serving Melissa, TX – Our Local Coverage Area
We serve Melissa and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Garage Conversion ADU in Melissa

Expect 4 to 7 months from demo to final inspection. The design and permit phase eats 2 – 3 weeks on its own, and finish selections are the most common cause of delay. Call (888) 343-9048 for a schedule built around your specific garage.
Yes. A habitable-room conversion with plumbing, electrical, and HVAC changes requires a permit and inspections in Melissa. We pull the permit and pass the inspections as part of the job, and we don’t start framing until it’s issued.
Sometimes, if you skip the bathroom and kitchenette and treat it as a studio. Once you add a bathroom, drain lines have to reach the main stack, which usually means cutting slab. Call us to walk your garage and find out which path yours supports.
Between $45,000 and $130,000, with the median job in the $70,000s. Size, plumbing distance, electrical capacity, and finish level move that number, and a written line-item estimate keeps surprises out of the process. Call (888) 343-9048 for an exact quote.
Our 730-Day Done Right Promise covers workmanship for two full years, in writing. If something isn’t done right, we come back and make it right. Many homeowners pair the conversion with exterior work like Concrete Driveways & Concrete Work in Melissa or Asphalt Driveways & Resurfacing in Melissa to finish the lot, and both fall under the same promise.
Ready to Price Your Garage Conversion ADU in Melissa?
Call (888) 343-9048 to schedule a free on-site estimate. We’ll measure your garage, check the slab and panel, and put a written line-item number in your hands with no obligation. Our technicians have up to 12 years of experience, our crew is background-checked and uniformed, and every project is backed in writing. Our Home Additions & ADU team covers all of Melissa and the surrounding area.
Written by the team at Groundwork Construction Co.