Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled
What a New Detached ADU in Anna, TX Costs and How Long It Takes
A new detached ADU in Anna, TX typically runs $45,000 – $130,000 and takes four to six months from the first foundation pour to the final inspection, depending on square footage, finishes, and how fast Collin County turns permits around. The structure is a fully separate, self-contained living unit on its own slab, with its own entry, kitchen, bath, and utility connections. Call (888) 343-9048 to set up a free on-site estimate and walk the lot with us before you commit to a number.
How We Build a New Detached ADU in Anna, Step by Step

Every ADU follows the same backbone, but the decisions land at different points, so here’s what actually happens and when you’ll need to weigh in.
- 1
Days 1 – 5: site walk and layout. We check setbacks, drainage, and where gas, water, and electric enter from the main house. You decide footprint and roof orientation here, because both affect how the unit sits against Anna’s summer sun.
- 2
Weeks 1 – 4: permitting and engineering. Plans go to the city, structural calcs get stamped, and we wait on the review. You approve finish packages while this runs so we’re not stalled.
- 3
Weeks 4 – 7: site prep, grading, and slab. Old fill gets compacted, footings and forms go in, then a post-tension slab pours and cures. This stage matters most on newer Anna lots with unsettled soil.
- 4
Weeks 7 – 18: framing, mechanicals, shell. Walls, roof, windows, and rough plumbing and electrical happen next, with inspections between each. You pick door and window ratings and HVAC sizing before we close the walls.
- 5
Weeks 18 – 26: finishes and final inspection. Drywall, flooring, cabinets, fixtures, paint, and landscaping tie-ins, then the final walkthrough and certificate of occupancy.
Our technicians have up to 12 years of experience, and most of that sits in framing and finish work on the sort of slab-on-grade homes we build ADUs beside every week. Background-checked, uniformed technicians run every phase, and the whole job is covered by our 730-Day Done Right Promise. If something isn’t right after we hand over the keys, we come back and fix it.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between for Your ADU
How the unit is built and finished drives the price more than anything else. Here’s what actually gets decided, with the honest trade-offs.
- Square footage and layout. A 400 – 600 sq ft studio costs less but limits who you can rent to. A 600 – 900 sq ft one-bedroom adds $15,000 – $30,000 but works for family, long-term tenants, or aging parents.
- Roof and structure. Stick-framed with standard shingles is the value pick. If you want the unit to hold up to North Texas hail and wind for the long haul, we spec impact-rated shingles and reinforce the frame tie-downs, which adds roughly $3,000 – $8,000.
- Windows and doors. Standard vinyl windows are affordable; impact-rated windows and a wind-rated exterior door cost more but cut storm damage and help with insurance. Homeowners often pair this with Paver Driveways in Anna to connect the pad to the main drive.
- Kitchen and bath fixtures. A Moen or Delta faucet set and an American Standard toilet keep budgets sane and parts easy to source. Upgrading to a Blanco sink or nicer hardware adds a few hundred per fixture but holds up better over rental turnover.
- HVAC and utilities. A dedicated mini-split or a standard split system, and whether you tie into the main house utilities or run separate meters. Separate metering is cleaner for tenants but costs more up front.
What a New Detached ADU Costs in Anna, TX

For a detached ADU in Anna, plan on $45,000 – $130,000. Where you land depends on five variables, and each one is a real line item in the written estimate.
- Size: Each additional 100 sq ft adds roughly $8,000 – $12,000 in framing, finishes, and mechanicals.
- Site conditions: Grading, drainage, or fill issues on newer lots push the low end up by $4,000 – $10,000.
- Utility runs: Trenching and running gas, water, and electric from the main house is $6,000 – $15,000 depending on distance.
- Finish grade: Builder-grade finishes sit near the low end; upgraded cabinetry, tile, and flooring push toward $130,000.
- Permit scope and inspections: A larger footprint or added plumbing means more review and inspection rounds.
Our free estimate is a written line-item quote, so you see exactly what’s included: foundation, framing, roofing, windows and doors, mechanicals, finishes, permits pulled and inspections passed, and cleanup. What it doesn’t cover is furniture, appliances if you choose to add them, or landscaping beyond tying in the grading. Upfront pricing, no surprises – the number you see is the number you pay, with 0% financing for 18 months and $1,000 off projects over $10,000 available. Call (888) 343-9048 for an exact quote.
See the difference
Before
After
Before
After
Before
AfterWhat Anna Homes and Lots Do to This Job
Anna sits on US-75 just north of McKinney, and most of the town’s single-family stock is new-build: slab-on-grade homes in the 2015-and-later master-planned tracts outward from the older core, with more phases going up every season. That changes an ADU build in two specific ways. First, the newer lots are filled ground on blackland clay, so expansive soil plus fresh fill means we’ve got to check compaction and drainage before the slab goes down, or the unit moves within a few years the same way foundations do. We regularly see yard ponding on the newest lots, which is why we grade away from the footprint before pouring. Second, because so much of Anna is under active construction and HOA oversight, we pull the permits and schedule inspections to keep the review moving alongside the subdivision’s building activity. Homeowners often pair this with Concrete Driveways & Concrete Work in Anna to bring the pad and grading into line. This is part of the wider Home Additions & ADU in Anna we cover for the area.
Serving Anna, TX – Our Local Coverage Area
We serve Anna and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in Anna

Most new detached ADU projects in Anna take four to six months, with permitting and slab curing as the two slowest stages. Call (888) 343-9048 and we’ll give you a stage-by-stage timeline based on your footprint.
Yes, we handle the permitting and inspections for your new detached ADU in Anna. We coordinate with the city and keep the review moving alongside existing subdivision activity. The written estimate shows permit scope up front.
Yes. Because a detached ADU sits on its own footprint, main-house plumbing and structure stay untouched, with only the utility runs being trenched out. Call (888) 343-9048 to walk your lot and confirm the layout.
Plan on $45,000 – $130,000 for a new detached ADU in Anna, depending on size, site conditions, utility runs, and finishes. Call (888) 343-9048 for a free written line-item quote.
Every new detached ADU we build in Anna is covered by our 730-Day Done Right Promise – if it’s not done right, we make it right. Calls are answered by a live person 24/7, so you reach us any time.
Get a Free Estimate for a New Detached ADU in Anna
Call (888) 343-9048 to schedule a free on-site estimate for a new detached ADU in Anna. We’ll walk the lot, confirm setback and drainage, and send a written line-item quote covering permits, foundation, and finishes – backed by the 730-Day Done Right Promise. Our team covers Anna and works as your single partner from foundation to finish line. See our Home Additions & ADU service for the full scope.
Written by the team at Groundwork Construction Co.